Colorado Department of Transportation
August 27, 2015
FTA granted a non-availability waiver for replacement gondola components procured by Mountain Village for a gondola refurbishment project.
Federal Register Notice (PDF)
August 27, 2015
FTA granted a non-availability waiver for replacement gondola components procured by Mountain Village for a gondola refurbishment project.
Federal Register Notice (PDF)
August 14, 2015
FTA granted a non-availability waiver for a Variable Refrigerant Flow (VRF) HVAC system for the Kansas City Streetcar’s Vehicle Maintenance Facility
Federal Register Notice (PDF)
August 27, 2015
FTA granted a non-availability waiver for replacement gondola components procured by Mountain Village for a gondola refurbishment project.
Federal Register Notice (PDF)
December 18, 2013
FTA granted a non-availability waiver for a Video-Ready Access Device (VRAD) cabinet for utility relocation work associated with the CATS LYNX Blue Line Extension project.
Federal Register Notice (PDF)
Title: Chief Operating Officer
Phase(s): Preliminary Engineering through Revenue Service
Category: Project Management
Date: April 21, 2009
1. BackgroundDate: ...
Title: Chief Operating Officer
Phase(s): Preliminary Engineering through Revenue Service
Category: Project Management
Date: April 21, 2009
1. BackgroundGrantees that are developing either new rail commuter projects or...
Title: Pre-Preliminary Engineering (PE) Review
Phase(s): Pre-PE / Entry into PE
Category: Project Management
Date: April 21, 2009
1. BackgroundThe Florida Department of Transportation (FDOT) is planning a commuter rail transit project to serve...
Project: Silver Line Phase III Project (Lessons-Learned No. 1)
Grantee: Massachusetts Bay Transportation Authority (BTA), Boston
Title: Combining/Sequencing Value Engineering Workshop with Scope, Schedule, and Cost Workshop
Phase(s): Preliminary Engineering...
Project: Silver Line Phase III Project (Lessons-Learned No. 2)
Grantee: Massachusetts Bay Transportation Authority (MBTA), Boston
Title: Integrating and updating cost estimate concurrently with design process
Phase(s): Preliminary Engineering
Category...