Regulations and Programs

756

Staged Infrastructure Implementation Impacts on Operations

Title: Staged Infrastructure Implementation Impacts on Operations

Phase(s): Final Design and Construction

Category: Management

Date: March 4, 1997

1. Background

In 1988, the Florida Department of Transportation (FDOT) purchased 81 miles of the CSX...

Safety Certification for Commuter Rail Projects

Date: July 10, 2015

Project Name: Central Florida Commuter Rail Transit (CFCRT) Project – Phase 1

Abstract: Safety Certification on Phase 1 of the CFCRT Project encountered a number of issues when certifying design, construction, testing, and pre-revenue operations....

Railroad Right-of-Way Issues

Title: Railroad Right-of-Way Issues

Phase(s): Preliminary Engineering

Category: Management

Date: June 23, 1997

1. Background

The Port Authority of Allegheny County's (PAT) Phase I Airport Busway/Wabash HOV Facility consists of a 7.0 mile exclusive...

Railroad Right-of-Way Acquisition

Title: Railroad Right-of-Way Acquisition

Phase(s): Pre-Preliminary Engineering

Category: Management

Date: March 2, 1998

1. Background

The Utah Transit Authority (UTA) is constructing a Light Rail Transit (TRAX) project running from a southern terminus...

QA/QC Procedures and Organization

Title: QA/QC Procedures and Organization

Phase(s): Pre-Preliminary Engineering and Preliminary Engineering

Category: Management

Date: September 16, 2008

1. Background

The Charlotte Area Transit System (CATS) South Corridor Light Rail Project (SCLRP...

Public Outreach Program Related to Right-of-Way Acquisition

Title: Public Outreach Program Related to Right-of-Way Acquisition

Phase(s): Construction

Category: Management

Date: April 4, 1997

1. Background

Light rail transit projects generally cross several political jurisdictions and involve the participation of...

Project Master Integrated Schedule (PMIS)

Title: Project Master Integrated Schedule (PMIS) – Schedule Management Plan

Phase(s): Final Design and Construction

Category: Management

Date: April 22, 2009

1. Background

Project requirements include plan development for each aspect of the project such...

Problems in Agency Coordination

Title: Problems in Agency Coordination

Phase(s): Pre-Preliminary Engineering, Preliminary Engineering and Final Design

Category: Management

Date: January 17, 1995

1. Background

The St. Louis Light Rail Project, known as MetroLink, involved the federal...

New York City Transit Accident and Prevention Program

Title: New York City Transit Accident and Prevention Program

Phase(s): Construction

Category: Management

Date: September 25, 1997

1. Background

The Queens Boulevard Connection Project is the largest new route's subway construction in the New York City...

Managing Undefined Scope

Title: Managing Undefined Scope

Phase(s): Preliminary Engineering

Category: Cost and Scope

Date: September 16, 2008

1. Background

The Charlotte Area Transit System (CATS) South Corridor Light Rail Project (SCLRP) is located in Mecklenburg County, North...