USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

U.S. Department of Transportation U.S. Department of Transportation Icon United States Department of Transportation United States Department of Transportation

General Content

Legacy ID
171
Show Effective Date
Off
Significant Regulatory Guidance
No

The Passenger Ferry Grant Program - 2013 NOFA

Date Posted: 8/21/2013

Closing Date: 10/21/2013

Program: The Passenger Ferry Grant Program

FTA Opportunity ID: FTA-2013-004-TPM

Opportunity Announcement Text: http://www.gpo.gov/fdsys/pkg/FR-2013-08-21/html/2013-20278.htm

Opportunity...

FTA and the SuperCircular Q&A

Participant Questions from RegistrationDoes OMB’s Uniform Administrative Requirements (SuperCircular) broaden, narrow, or supersede FTA’s circulars that were already issued?How does the SuperCircular fit into current regulations and laws?How do I determine my cognizant agency?What if a non-federal...

Management Category

Lesson Phase(s) Managing the Right of Way Process for Design-Build Contracts by co-locating the project team Engineering and Construction Quality Management Approach for Design-Build Contracts Engineering and Construction Third-Party...

Obtaining Railroad Operating Agreements Early

Title:  Chief Operating Officer

Phase(s):  Preliminary Engineering through Revenue Service 

Category:  Project Management

Date:  April 21, 2009

1. Background

Date:          ...

Technical Capacity

Title:  Chief Operating Officer

Phase(s):  Preliminary Engineering through Revenue Service 

Category:  Project Management

Date:  April 21, 2009

1. Background

Grantees that are developing either new rail commuter projects or...

Early Risk Assessment

Title:  Pre-Preliminary Engineering (PE) Review

Phase(s):  Pre-PE / Entry into PE

Category:  Project Management

Date:  April 21, 2009

1. Background

The Florida Department of Transportation (FDOT) is planning a commuter rail transit project to serve...

Combining and Sequencing VE with Scope-Cost-Schedule

Project: Silver Line Phase III Project (Lessons-Learned No. 1)

Grantee: Massachusetts Bay Transportation Authority (BTA), Boston

Title: Combining/Sequencing Value Engineering Workshop with Scope, Schedule, and Cost Workshop

Phase(s): Preliminary Engineering...

Solicitations and Bid Options

Title: Benefits of Structuring Bid Documents with Options

Phase(s): Final Design, Construction

Category: Management

Date: April 21, 2009

1. Background

During multiple risk assessments and throughout the ensuing project implementation phases, numerous...