You are here

Westside Purple Line Risk Assessment Lessons Learned

Over 200 "Lessons Learned" were collected from the following sources:

  • Metro Project Delivery Team
  • Metro Engineering
  • PB Team (Design/Design Services)
  • Construction Management Support Services Consultant

Collected from the following work:

  • Design/Build (Tunnels, Stations, Systems and Trackwork) Contract – In progress
  • Exploratory Shaft Contract – Construction Complete
  • Advanced Utility Relocation Contracts – In progress
  • MOW/NRV Building 61S Contract – In progress

“Lessons Learned” from recent experiences of other Transit Agencies considered

The “Lessons Learned” list has been consolidated into the following categories:

  • Design
  • Third Party
  • Construction
Submit Feedback >