Westside Purple Line Risk Assessment Lessons Learned
Over 200 "Lessons Learned" were collected from the following sources:
- Metro Project Delivery Team
- Metro Engineering
- PB Team (Design/Design Services)
- Construction Management Support Services Consultant
Collected from the following work:
- Design/Build (Tunnels, Stations, Systems and Trackwork) Contract – In progress
- Exploratory Shaft Contract – Construction Complete
- Advanced Utility Relocation Contracts – In progress
- MOW/NRV Building 61S Contract – In progress
“Lessons Learned” from recent experiences of other Transit Agencies considered
The “Lessons Learned” list has been consolidated into the following categories:
- Design
- Third Party
- Construction