Under Category 2, if a contract was executed prior to January 29, can a grantee receive reimbursement for future task orders that it might issue after this date?
FTA will make determinations on a case-specific basis, which may require recipients to submit contract documents to FTA for review. Generally, costs that are incurred after January 29th, such as by amending a contract, exercising options on a contract for additional work, or ordering previously un-budgeted tasks on an indefinite quantity contract, would not qualify for category 2, and would need to comply with all federal requirements, or would need to seek a waiver of specific requirements through the FTA docket as described in the March 29, 2013 Notice of Allocation. The docket is available on www.regulations.gov, and the docket number for calendar year 2013 is FTA–2013–0001. However, issuing future task orders on an existing contract for which funds were already committed (such as for storm clean-up/debris removal work) may be eligible under Category 2.