Can you explain the "timeline" section of the CWP? Are these suggested timelines or do they depict the timeframe that the FTA anticipates those given sections will take to complete?
The timelines provided in the sample Certification Work Plan (CWP) are examples. Each state should provide its own timeline to indicate when the state and FTA can expect the task identified in the CWP to be completed. In providing a timeline, the state should consider its operating environment, resources, and other circumstances that may affect the state’s timeline. FTA will review the timelines for reasonableness and work with states to determine an appropriate timeline if necessary.