13. Are there any reporting requirements if a project is approved under the PIPP?
Yes. A report is required one year after the completion of construction of a PIPP project. For projects that involve a private entity in the operations or maintenance of the project, a second report is required two years after the project begins revenue operations. Project sponsors will be responsible for submitting an independently prepared report that summarizes lessons learned from implementation of approved waiver or modification requests and from the PIPP process. These reports will evaluate the success of the process, its overall impact on the project, and recommend whether the waivers or modifications should be made routine through statutory or regulatory changes. The report should include an explanation of how the changes improved the delivery of the project.