07 What types of reviews will FTA undertake to approve entry into Engineering?

By law, FTA evaluates and rates Capital Investment Grants Program New Starts or Core Capacity projects prior to allowing them into the Engineering phase. FTA evaluates and develops ratings for the project justification and local financial commitment criteria.

FTA also reviews the project sponsor’s Project Management Plan and subplans to ensure that the sponsor has the technical capacity and capability to deliverthe project.  Lastly, FTA reviews the project definition, scope, cost and schedule for reasonableness, undertakes and completes a risk assessment. These reviews may be expedited based on factors including the complexity of the project and the project sponsor’s management capacity and capability.