Can a grantee reallocate funds for a portion of the scope of a single project? If this scenario is permitted, do the portions reallocated have to align with the budget breakdown approved in the original application?

Yes, as noted in the previous answer, it is permissible for a recipient to request the reallocation of a portion of a project’s proposed scope, provided that the remaining scope results in a viable project with an independent resilience benefit. In this case, the recipient should submit a revised project budget breakdown reflecting the reduced scope. 